INTERNSHIP REPORT ON INDUSTRIAL TRAINING AT GHORASHAL TRAINING CENTER (GTC) My Interning Book Fornt Pages

BANGLADESH POWER DEVLOPMENT BOARD(GTC)

INTERNSHIP REPORT ON INDUSTRIAL TRAINING AT GHORASHAL TRAINING CENTER (GTC)
*********** GTC Computer Simulation Lab ***********
*********** GTC Computer Simulation Lab ***********



INTERNSHIP REPORT ON INDUSTRIAL TRAINING AT GHORASHAL TRAINING CENTER (GTC)

An Internship Report submitted in partial fulfillment of the requirements for the Award of Degree of
Bachelor of Science in Electrical and Electronic Engineering



by
Md Idris Ali
ID: 2015100500009




Supervised by
ENGR. sHAHID JAMAN
Lecturer Coordinator (Evening)
Department EEE, SEU


                                                       
Department of Electrical and Electronic Engineering School of Science and Engineering
Southeast University


May 2019

----------------------------------------------------------------------------------


Certification

This is to certify that this Internship entitled Internship Report on Industrial Training at Ghorashal Training Center (GTC) is done by the following student under my direct supervision and this work has been carried out by them in the Ghorashal Power Plant in partial fulfillment of the requirements for the degree of Bachelor of Science in Electrical and Electronic Engineering. The presentation of the work was held on 23th May 2019.




Signature of the candidates




_____________________
Md Idris Ali
ID: 2015100500009











Countersigned






__________________________
Engr  Shahid Jaman
Supervisor
Lecturer & Coordinator (Evening)  
Department of Electrical and Electronic Engineering
School of Science and Engineering
Southeast University, Dhaka, Bangladesh.


----------------------------------------------------------------------------------



The Internship entitled Internship Reports On Industrial Training at Ghorashal Training Center (GTC)” submitted by Md  Idris  Ali, ID:2015100500009 Session: Summer 2015 has been accepted as satisfactory in partial fulfillment of the requirements for the degree of Bachelor of Science in Electrical and Electronic Engineering on 23 May, 2019.

BOARD OF EXAMINERS




__________________________________
Prof. Dr. Engr. Muhibul Haque Bhuyan                                                          Chairman      Professor and Chairman                                                                                                                     
Department of EEE, SEU









_________________________________
Engr. Shahid Jaman                                                                                            Supervisor
Lecturer & Coordinator (Evening)                                                                                                    
Department of EEE, SEU








________________________________
Engr. Azwad Tamir                                                                                      Internal Member
Lecturer                                                                                  
Department of EEE, SEU





H


 --------------------------------------------------------------------------------

Dedicated to
Our Parents













--------------------------------------------------------------------------------- 

CONTENTS
List of Figures
13-14
List of Table
15
List of Abbreviation
16
Acknowledgement
17
Abstract
18

Chapter 1
Introduction

19-22
1.1
Introduction
20
1.2
Background of Ghorashal Power Station
20
1.3
Company Objective
20
1.4
Generation Details
21
1.5
Repowering project
21
1.6
About Ghorashal Training Centre
21
1.7
Objective of the Internship
22
1.8
Future project of GPS
22

Chapter  2
Different Types of Power Plant

23-39
2.1
Steam Turbine Power Plant
24
2.1.1
Introduction to steam turbine
24
2.1.2
Air collection
24
2.1.3
Forced draft fan
24
2.1.4
Air pre-heater
24
2.1.5
Flow transmitter
25
2.1.6
Fuel gas
25
2.1.7
Line gas control valve
25
2.1.8
Gas flow meter
25
2.1.9
Gas heater
25
2.1.10
Water collection
25
2.1.11
Pump
25
2.1.12
Water Purifying basin
26
2.1.13
Water filter house
26
2.1.14
De-Mineralized process
27
2.1.15
Boiler
27
2.1.16
Water tube boiler
27
2.1.17
Ignition
27
2.1.18
Burner
28
2.1.19
Boiler drum
28
2.1.20
Safety valve
28
2.1.21
Pressure Transmitter
28
2.1.22
Boiler efficiency:
29
2.1.23
Stack
29
2.1.24
Steam turbine
29
2.1.25
Sections of steam turbine
29
2.1.26
Operation and Maintenance
30
2.2
Gas Turbine Power Plant
30
2.2.1
Introduction
30
2.2.2
Working Principle
31
2.2.3
Gas turbine Components
31
2.2.3.a
Air Inlet Equipment
32
2.2.3.b
Compressor
32
2.2.3.c
Centrifugal Compressor
32
2.2.3.d
Combustion System
32
2.2.3.e
Turbine
33
2.2.3.f
Gas path Description
33
2.2.3.g
Turbine Base & support
34
2.2.4
Compressor Section
34
2.2.5
Combustion System
35
2.3
Combine Cycle Power Plant (CCPP)
35
2.3.1
Combine Cycle
35
2.3.2
How a Combined-Cycle Power Plant Produces Electricity
35
2.3.3
Heat recovery system captures exhaust.
36
2.3.4
Steam turbine delivers additional electricity
36
2.3.5
Main Components
36
2.3.6
Operating Mode
37
2.3.7
Schemes of Combined Cycle
37
2.3.8
Combined Cycle Advantages
37






Chapter 3
Substation
38-50
3.1
Introduction of substation     
39
3.2
Overview of Power Transmission and Distribution     
39
3.3
Voltage Classes of GPS   
40
3.4
Grid Voltage and Distribution Voltage of GPS          
40
3.4.1
Grid Voltage
40
3.4.2
Distribution Voltage
40
3.5
System Components:
40
3.6
Transformer
41
3.6.1
Power Transformer
41
3.6.1.a
Radiator
41
3.6.1.b
Breather
42
3.6.1.c
Bushing
42
3.6.2
Potential Transformer
42
3.6.3
Current Transformer
42
3.6.4
Unit Transformer
42
3.6.5
Intermediate Potential Transformer
42
3.7
Maintenance of Transformer
43
3.8
Distribution Transformers
43
3.9
Substation Transformers
43
3.10
C.T (Current Transformer)
44
3.11
P.T (Potential transformer)
44
3.12
Isolator
44
3.12.1
Isolator can be in three types
44
3.13
Power Circuit Breaker
44
3.13.1
Minimum Oil Circuit Breaker
45
3.13.2
Maintenance of Minimum Oil Circuit Breaker
45
3.13.3
SF6 Circuit Breaker
45
3.14
Earthling Switch
45
3.14.1
Operating sequence for maintenance purpose
46
3.15
Lightning Arresters
46
3.15.1
Rod Gap Lightning Arrester
46
3.15.2
Horn Gap Lightning Arrester
46
3.16
Relay
46
3.16.1
Electrical Relay
47
3.16.2
Electronics Overload Relay
47
3.16.3
Buchholz relay
47
3.17
Power Capacitors
47
3.18
Sub-station Auxiliary Supply
47
3.19
Bus Bar
48
3.20
Types of bus bar
48
3.21
Insulator
48
3.21.1
Pin Type Insulators
48
3.21.2
Suspension Type Insulator
49
3.22
Transmission Line
49
3.22.1
Different Transmission Line Pole Structure
49
3.23
Wave Trap
49
3.24
Cables
50
3.25
Conclusion
50





Chapter 4
Practical overview
51-77
4.1
Chemical Plant
52
4.1.1
Step-1 coagulation                    
51
4.1.2
Step-2 mechanical/sand filter
51
4.1.3
Step-3 caption exchanger
53
4.1.4
Step-4 Degasified/Decarbonizes
53
4.1.5
Step-5 Anion Exchanger
53
4.1.6
STEP-6 Mixed Bed Exchanger
54
4.2
Quality of De-Mineralized water
54
4.3
Different types of measuring instrument
55
4.4
Condenser                                          
56
4.5
Boiler
56
4.6
Boiler Pipe Line
57
4.7
Furnace
57
4.8
Turbine
58
4.9
Bearing
58
4.10
Generator
59
4.11
Generator protection
60
4.12
Gas Turbine
60
4.13
Power Generation Efficiency
61
4.14
Heat Rate
62
4.15
Simulation Practical Lab
62
4.16
Transformer
63
4.16.1
Potential Transformer
63
4.16.2
Power Transformer
64
4.16.2.a
Radiator
65
4.16.2.b
Breather
66
4.16.2.c
Bushing
66
4.16.2.d
Current Transformer
66
4.16.3
Unit Transformer
67
4.17
Isolator
67
4.18
Power Circuit Breaker
68
4.18.1
Minimum Oil Circuit Breaker
68
4.18.2
SF6 Circuit Breaker
69
4.19
Earthling Switch
69
4.20
Lightning Arresters
70
4.20.1
Rod Gap Lightning Arrester
70
4.20.2
Horn Gap Lightning Arrester
70
4.21
Relay
71
4.22
Bus Bar
71
4.23
Insulator
72
4.23.1
Pin Type Insulators
72
4.23.2
Suspension Type Insulator
72
4.24
Transmission Line
73
4.25
Wave Trap
73
4.26
Control Room
74
4.27
Cables
74
4.28
Feed water and drum level control
75
4.29
Safety valve
75
4.30
Pressure gauge
75
4.31
Flame detector
76
4.32
Air flow transmitter
76
4.33
Turbine over temperature
76
4.34
Turbine over speed
76
4.35
Low lube oil pressure
77
4.36
Excessive vibration
77







CHAPTER 5
Personal achievement
78-81
5.1
My Achievement
79






CHAPTER 6
Conclusion
82-83


6.1
Problem faced
83
6.2
Discussion

Day Wise Visit
83
84-99


Reference
100





 ------------------------------------------------------------------------------






LIST OF FIGURES
Figure
Figure Caption
Page
2.1
Working principal of steam turbine
24
2.2
Gas Turbine electric power generation
31
2.3
Gas burner connection and transition section
33
2.4
Gas-Steam Combine Cycle Power System Equipment &Processing Flow Diagram.
36
3.1
Distribution asset in national network
39
3.2
Intermediate potential transformer
42
3.3
132KV double circuit bus bar.
48
3.4
Pin type insulator for 33KV line.
48
3.5
Pole structure of transmission line.
49
4.1
Clarifier or Rectifier.
52
4.2
Mechanical/Sand Filter
52
4.3
cation exchanger
53
4.4
Degasifier / decarbonizes
53
4.5
Anion exchanger
55
4.6
Flow diagram of water treatment
55
4.7
Condenser of unit -4
56
4.8
pipe line of boiler
57
4.9
Boiler furnace unit 5
57
4.10
Blades of steam turbine at unit 6
58
4.11
Bearing of steam turbine at unit 6.
58
4.12
practical view of generator at unit 6
59
4.13
inside view of stator at unit 6
59
4.14
practical view of rotor at unit 6
59
4.15
gas turbine at combine cycle project of unit 7
60
4.16
unit -7 CCPP at GPS
60
4.17
Practical view of Combine cycle generation process presented in block diagram.
61
4.18
simulation lab
62
4.19
generic Gas Turbine Simulator (1)
63
4.20
generic Gas Turbine Simulator (2)
63
4.21
Potential transformer with nameplate of the GPS substation.
63
4.22
Tap changing power transformer.
65
4.23
Radiator of a power transformer.
65
4.24
Breather of a power transformer
66
4.25
Bushing of power transformer.
66
4.26
Current transformer with nameplate of the GPS substation.
66
4.27
Single phase unit transformer.
67
4.28
Horizontal center break isolator from GPS.
67
4.29
Minimum oil CB.
68
4.30
SF6 circuit breaker
69
4.31
Earthling switch used in 132KV line
69
4.32
Rod gap type lightning arrester of GPS.
70
4.33
Horn type of lightning arrester.
70
4.34
132KV double circuit bus bar.
71
4.35
Suspension type insulator observed from GTC substation.
72
4.36
Sub-station of 230kv/132kv.
73
4.37
Wave trap used on GPS substation.
73
4.38
Rectifier used for battery charging purpose.
74
    5.1
Boiler
79
    5.2
Turbine
80
    5.3
Working time
81





List of tables

Table
Table caption

Page
Table 1.1
generation details of BPDB at Ghorashal
21
Table 4.1
132 kV Single phase outdoor type potential transformers.

73
Table 4.2
Insulters voltage level with its number of disk

          83
Table 4.3
Different Cables Used at GPS Substation

86



--------------------------------------------------------------------------------- 









List of Abbreviations
                                        
GTC= Ghorashal training center
GPS= Ghorashal power station
BPDB=Bangladesh power development board
CCPP = Combined Cycle Power Plant
CT = Current Transformer
PT = Potential Transformer
CB = Circuit Breaker
MW = Mega Watt
LPT = Low pressure turbine
IPT = Intermediate pressure turbine
HPT = High pressure turbine
ONAN = Oil Natural Air Natural, without pumps and fans
ONAF = Oil Natural Air Forced, without pumps for oil, with fans for air



 --------------------------------------------------------------------------




ACKNOWLEDGEMENT

First of all, we give thanks to Allah. Then we would like to take this opportunity to express our appreciation and gratitude to our internship supervisor Engr Shahid Jaman, Lecturer & Coordinator (Evening) Department of EEE for being dedicated in supporting, motivating and guiding us through this internship. This internship can’t be done without his useful advice and helps. Also thank you very much for giving us opportunity to choose this internship.
We also want to convey our thankfulness to Prof. Dr. Engr. Muhibul Haque Bhuyan, Chairman of the Department of EEE for his help, support and constant encouragement.
Apart from that, we would like to thank our entire friends for sharing knowledge; information and helping us in making this internship a success. Also thanks for lending us some tools and equipment.
To our beloved family, we want to give them our deepest love and gratitude for being very supportive and also for their inspiration and encouragement during our studies in this University.





--------------------------------------------------------------------------------------





ABSTRACT

This internship at Ghorashal Training Center (GTC) located on the right bank of the river Shitalakshya from 8th January 2019 to 24th January 2019 and this internship report is the result of those 15 days’ attachment with the GTC, Ghorashal power station owns the largest power station in Bangladesh. The installed capacity by its 7 units is 1315 MW.  My duration of stay was divided to work in five sections as generator, sub-station, CCPP, I & C and operation. During my internship I gathered practical knowledge about production of electricity, operation, CCPP, major equipment’s e.g. Generator, Transformer and Switchgear equipment’s required for distribution and protection of the system. Protection and controlling of the equipment’s of the power station is a very important and complicated task. With the help of the plant engineers I observed the control room and protective equipment’s such as: relays (digital and electrical), circuit breakers etc. very closely and understood the functions and controlling system of those equipment’s. Substation is an important part of a power station to distribute power and protection purpose. I acquired knowledge about various types of transformers, bus-bars, circuit breakers (SF6 and Oil), lightning arresters, CT, PT and other equipment’s of the substation which were clearly taught and shown by the senior engineers of the substation of GPS. We learn about the water management system for all power generating units of GTC. Inside the report I describe about my experience at GTC.


---------------------------------------------------------------------------------------------------------









SHARE THIS
Previous Post
Next Post